Memory Care
I was out for a walk through in a new Memory Care. My State any long term health care, hospital, day care, public school, prison must be inspected by a State Inspector for plumbing, Special long term health division of the State, DCFIS for day care.
This job a so called plumbing contractor started, screwed up the ground rough a couple of times, got fired and another plumbing company was hired to complete the roughs and trim it out.
In the pictures the first plumbing contractor missed the walls with PEX in the 2 mech. rooms. So the second plumber broke out floor, concreted in below the pex & CPVC you see and included a floor drain in case water gets in this trough. No they plan to use diamond plate aluminum to make a cover for the area.
First pict, the plate will go to the one CPVC line that runns perpendicular to the rest.
The second picture, things poke up so much they plan to make the plate bend up in the center since the conversions stick above the floor and cut out an access for the clean out.
Told them they were real lucky the State had seen this. I would have forced the follow up contractor to bust out concrete to a wall, bring the PEX up that wall, reconnect and go back under the concrete to where they needed to be.
I was almost sick seeing this.
This job a so called plumbing contractor started, screwed up the ground rough a couple of times, got fired and another plumbing company was hired to complete the roughs and trim it out.
In the pictures the first plumbing contractor missed the walls with PEX in the 2 mech. rooms. So the second plumber broke out floor, concreted in below the pex & CPVC you see and included a floor drain in case water gets in this trough. No they plan to use diamond plate aluminum to make a cover for the area.
First pict, the plate will go to the one CPVC line that runns perpendicular to the rest.
The second picture, things poke up so much they plan to make the plate bend up in the center since the conversions stick above the floor and cut out an access for the clean out.
Told them they were real lucky the State had seen this. I would have forced the follow up contractor to bust out concrete to a wall, bring the PEX up that wall, reconnect and go back under the concrete to where they needed to be.
I was almost sick seeing this.